— Case Studies —

Aluminium Casting Conversion for Antenna Mainframe

A UK foundry, Finecast Foundry Ltd, produced an extraordinary stabilised antenna platform as a lightweight cast component – converting the part from a fabrication has reduced weight and increased strength.

Component

  • Lightweight stabilised antenna platform main frame, 80kg (casting), 63kg (finish machined) for use in the naval surveillance market
  • Dimensions 1415mm (length) x 1055mm (width) x 965mm (height) Nominal wall thickness of 5mm

Alloy

  • Aluminium BSL169 (A357 T6)

Casting Process

  • Gravity poured precision sand casting

Customer Requirements

  • The creation of a smaller, lighter, stiffer and stronger radar self-stabilising main frame
  • Improve quality
  • Reduce lead time to market to meet quality ISIR requirements
  • Reduce costs
  • Reduce weight of component

Previous Part

  • Fabrication

Outcome

  • From the original concept meeting, delivery of the tooling and first main frame cast was achieved in four months. Thus lead time was greatly reduce compared the fabrication methods.
  • The initial main frame and other castings were right first time, and successfully completed the first assembly and static simulation tests without problems.
  • The total project assembly weight targets were as designed, and lighter than fabrications for carrying the same antenna payload. Only minor machining adjustments have been made to the project.
  • The casting option has proven to maintain dimensional repeatability.
  • The lighter weight frame has achieved increased stiffness and strength, compared to heavier fabrications.
  • The achievement of thin wall casting dimensions, that are not traditionally considered able to be cast in sand, can now be produced in a precision sand foundry process.

Challenges

  • Low wall thickness for the size of the casting, with no draft allowances
  • The calculated modulus was 2.9mm, on a par with casting a 5mm plate (2160 x 2160mm with holes)
  • Fill distances, T section rules, solidification times, non turbulent flow and mould space were significant factors
  • Because of the physical size of the tooling, cope and drag 2.2 x 2.2m moulds, restrictions of taper, a total of 33, multi loose piece core boxes had to be manufactured in a short lead time.
  • Being a multi core assembly, it is essential that the foundation (drag) is maintained as flat as possible.
  • The main frame and roll frame required in line boring together.

Method

  • To complete delivery in time, the project utilised two patternshops working from one CAD reference model.
  • Additional hand ladle capacity was added to complete the required quantity of 450kg of metal.
  • For reduction of quench distortion after solution, the casting was heat treated with the running system still attached minus risers.
  • The final finished casting was anodised/anocromed, painted and delivered to the customer for assembly.